Kelantan And Terengganu ECRL Project Affected By Floods

Anis

Share via


The floods last week impacted around 70% of the construction work at sections 1 and 2 of the East Coast Rail Line (ECRL), which spans 82 kilometres from Tunjong here to Setiu in Terengganu. Mohd Azemi Abdullah, construction manager of Malaysia Rail Link Sdn Bhd (MRL) (sections 1 and 2), stated that the impacted regions entailed preliminary operations such as forest removal and were in low-lying areas.


"The earthworks have been impacted by rainwater (flooding), and we are unable to work," he told reporters yesterday after presenting donations to flood victims at the Bukit Abal Penggawa office. Mohd Azemi, on the other hand, stated that the floods had no effect on the construction activity, including the bridge construction.


"We only have to stop operations if it rains, except for work at a height of more than 2m from the ground level," he explained. According to reports, Kelantan suffered heavy rainfall last week, inundating numerous areas of the state. On December 18, the state Drainage and Irrigation Department recorded 627mm of rainfall intensity in Kampung Wakaf Raja, Bukit Yong near Pasir Puteh, the highest since 1967.

Tagged:

ECRL
East Coast Rail Link (ECRL)
2022 floods
Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

Related News

Auto News
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.

24-06-2025
Auto News
ECRL Is More Than 60% Complete - Malaysia Rail

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News
ECRL Project Progress Surpasses 56% - Loke

ECRL Project Progress Surpasses 56% - Loke

ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.

11-12-2023
Auto News
ECRL Kelantan Expected To Be Completed Six Months Earlier

ECRL Kelantan Expected To Be Completed Six Months Earlier

The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.

26-06-2023
Auto News
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.

12-04-2023
Auto News
ECRL Project In Terengganu Reaches 55% Progress

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023
Auto News
ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL project's Kuantan Tunnel will be completed by the end of April.

08-03-2023
Auto News
ECRL Land-Clearing; Enforcement Due To SOP Breach - Selangor MB’s Aide

ECRL Land-Clearing; Enforcement Due To SOP Breach - Selangor MB’s Aide

Selangor Forestry Department found that the alleged land clearing activities in the Selangor State Park are part of the ECRL project.

06-02-2023

Latest News

Auto News
JPJeID Registration Now Available at Driving Institutes

JPJeID Registration Now Available at Driving Institutes

JPJeID registration is now available at all driving institutes, streamlining access to MySIKAP and MyJPJ services.

Auto News
Couple Killed In Ford Mustang Crash Near Segamat

Couple Killed In Ford Mustang Crash Near Segamat

A married couple died after their Ford Mustang crashed into an electric pole along Jalan Segamat-Kuantan.

05-08-2025
Auto News
Proton e.MAS 5 ‘MISI 5’ National Tour – Aug to Oct, Launching Soon?

Proton e.MAS 5 ‘MISI 5’ National Tour – Aug to Oct, Launching Soon?

The upcoming Proton e.MAS 5 is going on a ‘MISI 5’ national tour from August to October, 2025. Launch imminent?

05-08-2025
Auto News
MoF: Fuel Subsidy Rollout Under Testing, Launches End-Sept

MoF: Fuel Subsidy Rollout Under Testing, Launches End-Sept

MoF is finalising the targeted fuel subsidy system, with full rollout details expected by end-Sept.

Auto News
Ferraris, Lambos Among 1,000 Untaxed Vehicles - JPJ

Ferraris, Lambos Among 1,000 Untaxed Vehicles - JPJ

JPJ flags over 1,000 luxury cars, including Ferraris and Lambos, for missing road tax and insurance.

05-08-2025
Auto News
KLIA Apologises After Aerotrain Breaks Down Again

KLIA Apologises After Aerotrain Breaks Down Again

KLIA’s Aerotrain stalled for 15 minutes due to a door glitch, prompting an apology and public frustration.

05-08-2025
Auto News
Amir Hamzah: PADU at the Core of RON95 Subsidy Implementation

Amir Hamzah: PADU at the Core of RON95 Subsidy Implementation

With over 30 million individual profiles, PADU will guide MOF’s effort to roll out a more precise RON95 petrol subsidy.

Auto News
KPDN Probes SG Driver Sighted Pumping RON95 in Johor

KPDN Probes SG Driver Sighted Pumping RON95 in Johor

KPDN is probing a viral incident where a Singapore-registered car was seen pumping subsidised RON95 fuel.