ECRL Project In Terengganu Reaches 55% Progress
-full.jpg)
Malaysia Railway Link Sdn Bhd said in a statement the construction of East Coast Rail Link (ECRL) Project in Terengganu has reached a progress level of 55.21 percent.
The route in Terengganu holds the longest line compared to the other three states namely Kelantan, Pahang and Selangor which is 275 KM long from a total of 665 KM and estimated to cost a sum of RM 50.27 billion.
So far, the construction work on the said project in Terengganu is set to be on track and scheduled to be fully completed by December 2026.

From there it includes the construction of six stations namely Jerteh, Bandar Permaisuri, Kuala Terengganu and Kemasik which function as passenger stations while Dungun and Chukai are for the purpose of passengers and cargo.
Separately, construction work for the entire 665 KM ECRL line project from Kota Bharu, Kelantan to Port Klang, Selangor has an overall progress level of 40.81 percent, according to Malaysia Rail Link (MRL) CEO Datuk Seri Darwis Abdul Razak.
"Out of that amount, there are 21 km of tunnels in Selangor and there are approximately 31 km of bridges that will be built in the Selangor line," he added.

Meanwhile, the East Coast Rail Link (ECRL) project involving the Selangor line is considered to be the most critical compared to the other three states, as reported by local news online.
He further stated that the construction of the C1B alignment in the northern part of the state is seen as complex because it involves various types of construction in addition to bridges and tunnels.
"I say it is critical because we started this ECRL project in 2017, stopped for a while in July 2018 and resumed in April 2019.
‘’We got approval from the state government for us to implement the ECRL project through the northern line starting December 2021 and we can only start construction work with good cooperation from all state and federal departments and agencies which give us approval in June 2022,’’ the exec said.
The service is expected to be operational in January 2027 and can accommodate 5.6 million passengers a year aside from also can carry 440 passengers for a trip involving six carriages.
Written By
Jesica Sendai
from 9 to 5 grinder to 'racing' her way in the automotive industry through editorial work.
JPJ Running Numbers
KUALA LUMPUR
VQD6251
SELANGOR
BSK8460
JOHOR
JYM7844
PULAU PINANG
PRW5639
PERAK
APD3739
PAHANG
CFE4586
KEDAH
KGD4342
NEGERI SEMBILAN
NEH8960
KOTA KINABALU
SJP2851
KUCHING
QAB7425M
Last updated 16 Dec, 2025
Fuel Price
Petrol
RON 95
RM 2.64
-0.02
RON 97
RM 3.27
-0.02
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.06
-0.02
EURO 5 B7
RM 3.26
-0.02
Last updated 11 Dec, 2025
Related News
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses
The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.
14-10-2025
ECRL Project Hits 87% Completion by August 2025 – MoT
The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.
23-09-2025
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO
MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.
24-06-2025
ECRL Is More Than 60% Complete - Malaysia Rail
ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.
25-03-2024
ECRL Project Progress Surpasses 56% - Loke
ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.
11-12-2023
ECRL Kelantan Expected To Be Completed Six Months Earlier
The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.
26-06-2023
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke
The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.
12-04-2023
ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%
ECRL project's Kuantan Tunnel will be completed by the end of April.
08-03-2023
Latest News
Shah Alam LRT Launch Delayed To Avoid Another 2021 Kelana Jaya Crash
Prasarana delays the Shah Alam LRT opening, prioritising passenger safety and thorough testing after past LRT mishaps.
15-12-2025
Federal Highway Won’t Be Upgraded, Costs Deemed Too High
Despite worsening traffic conditions, the Federal Highway will not be upgraded, with the government citing high costs.
15-12-2025
Bollards Are There for Your Safety, Not Decoration - DBKL
DBKL is reminding the public that bollards play a crucial role in keeping pedestrians safe.
15-12-2025
Experts Call For Stricter Rules, Defensive Driving As Road Deaths Rise
Negligent driving caused over 1,200 fatalities this year, prompting calls for tougher enforcement and smarter driver education.
15-12-2025
New KTM Komuter Timetable Starts Jan 1 Amid Track Works
KTMB will roll out a revised KTM Komuter schedule from Jan 1 due to ongoing KVDT2 works.
15-12-2025
Govt Rules Out Tiered RON95 Pricing After 300 litres
Government rules out tiered RON95 prices under BUDI95, keeps RM1.99 for first 300 litres
12-12-2025
Hyundai Partners EON, Expands Local Network
Hyundai and EON have signed a LOI to open two new dealerships in Klang Valley and Penang.
12-12-2025
Perodua Traz/Nexis D66B Set to Debut on December 17
The long-awaited Perodua Traz/Nexis D66B SUV is set to make its official debut later on December 17, 2025.
12-12-2025
Show More
trending_flat