ECRL Project In Terengganu Reaches 55% Progress
-full.jpg)
Malaysia Railway Link Sdn Bhd said in a statement the construction of East Coast Rail Link (ECRL) Project in Terengganu has reached a progress level of 55.21 percent.
The route in Terengganu holds the longest line compared to the other three states namely Kelantan, Pahang and Selangor which is 275 KM long from a total of 665 KM and estimated to cost a sum of RM 50.27 billion.
So far, the construction work on the said project in Terengganu is set to be on track and scheduled to be fully completed by December 2026.

From there it includes the construction of six stations namely Jerteh, Bandar Permaisuri, Kuala Terengganu and Kemasik which function as passenger stations while Dungun and Chukai are for the purpose of passengers and cargo.
Separately, construction work for the entire 665 KM ECRL line project from Kota Bharu, Kelantan to Port Klang, Selangor has an overall progress level of 40.81 percent, according to Malaysia Rail Link (MRL) CEO Datuk Seri Darwis Abdul Razak.
"Out of that amount, there are 21 km of tunnels in Selangor and there are approximately 31 km of bridges that will be built in the Selangor line," he added.

Meanwhile, the East Coast Rail Link (ECRL) project involving the Selangor line is considered to be the most critical compared to the other three states, as reported by local news online.
He further stated that the construction of the C1B alignment in the northern part of the state is seen as complex because it involves various types of construction in addition to bridges and tunnels.
"I say it is critical because we started this ECRL project in 2017, stopped for a while in July 2018 and resumed in April 2019.
‘’We got approval from the state government for us to implement the ECRL project through the northern line starting December 2021 and we can only start construction work with good cooperation from all state and federal departments and agencies which give us approval in June 2022,’’ the exec said.
The service is expected to be operational in January 2027 and can accommodate 5.6 million passengers a year aside from also can carry 440 passengers for a trip involving six carriages.
Written By
Jesica Sendai
from 9 to 5 grinder to 'racing' her way in the automotive industry through editorial work.
JPJ Running Numbers
KUALA LUMPUR
VRQ2895
SELANGOR
BST7265
JOHOR
JE3258J
PULAU PINANG
PSF5773
PERAK
APL4891
PAHANG
CFH7448
KEDAH
KGJ1329
NEGERI SEMBILAN
NEL8562
KOTA KINABALU
SJU1428
KUCHING
QAB5707P
Last updated 18 Sep, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses
The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.
14-10-2025
ECRL Project Hits 87% Completion by August 2025 – MoT
The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.
23-09-2025
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO
MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.
24-06-2025
ECRL Is More Than 60% Complete - Malaysia Rail
ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.
25-03-2024
ECRL Project Progress Surpasses 56% - Loke
ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.
11-12-2023
ECRL Kelantan Expected To Be Completed Six Months Earlier
The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.
26-06-2023
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke
The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.
12-04-2023
ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%
ECRL project's Kuantan Tunnel will be completed by the end of April.
08-03-2023
Latest News
Perodua Ativa X Is Now RM53K - Would You Still Buy A Myvi?
The Perodua Ativa X is now RM53,000 after a RM9,500 rebate, just RM1,900 below the Myvi 1.5 H. Here's what you get with each.
17-09-2026
BUDI Diesel Can Now Be Transferred Beyond Family - Here's How It Works
BUDI Diesel eligibility can now be transferred beyond immediate family to the actual vehicle user. Here's who qualifies, how to apply and the Sept 27 deadline.
17-09-2026
Puspakom Has More Rivals Now. So Why Aren't Car Inspections Getting Cheaper?
Puspakom now has rivals for M.V.15 ownership transfer inspections, but fees won't get cheaper. Here's why JPJ is keeping rates standardised.
15-09-2026
If You're In Penang And Eyeing A Suzuki, There's A New Showroom To Check Out
Suzuki has opened a new RM1 million dealership in Juru, Penang, expanding its Malaysian network to 14 sales outlets and 13 service centres.
14-09-2026
Malaysia Has More Car Brands Than Ever. So Why Do We Still Choose Proton And Perodua?
Proton and Perodua account for nearly 63% of Malaysia's new car registrations in 2026. Here's why national brands still dominate despite growing competition.
14-09-2026
40,595 Summonses, RM12.18 Million Unpaid. JPJ's Patience Is Running Out
JPJ has given 945 transport companies 14 days to settle 40,595 outstanding summonses worth RM12.18 million or face tougher enforcement.
11-09-2026
Use The Kelana Jaya LRT? Here's Why Some Stations Won't Open Until 9.30AM
Kelana Jaya LRT track replacement works run from Sept 2026 to Sept 2027. Check the affected stations, Sunday dates and 9.30AM opening times.
10-09-2026
Your Car's Windscreen Isn't Just Glass, And This Crash Test Shows Why
Malaysia's first live windscreen crash test at MIROS shows why proper installation, adhesive and curing time matter for vehicle safety.
10-09-2026
Show More
trending_flat