ENZHMS
Link Copiedcheck_circle
Auto News

ECRL Project In Terengganu Reaches 55% Progress

Jesica Sendai

Share via




Malaysia Railway Link Sdn Bhd said in a statement the construction of East Coast Rail Link (ECRL) Project in Terengganu has reached a progress level of 55.21 percent.  


The route in Terengganu holds the longest line compared to the other three states namely Kelantan, Pahang and Selangor which is 275 KM long from a total of 665 KM and estimated to  cost a sum of RM 50.27 billion. 


So far, the construction work on the said project in Terengganu is set to be on track and scheduled to be fully completed by December 2026.





From there it includes the construction of six stations namely Jerteh, Bandar Permaisuri, Kuala Terengganu and Kemasik which function as passenger stations while Dungun and Chukai are for the purpose of passengers and cargo.


Separately, construction work for the entire 665 KM ECRL line project from Kota Bharu, Kelantan to Port Klang, Selangor has an overall progress level of 40.81 percent, according to Malaysia Rail Link (MRL) CEO Datuk Seri Darwis Abdul Razak. 


"Out of that amount, there are 21 km of tunnels in Selangor and there are approximately 31 km of bridges that will be built in the Selangor line," he added. 





Meanwhile, the East Coast Rail Link (ECRL) project involving the Selangor line is considered to be the most critical compared to the other three states, as reported by local news online.


He further stated that the construction of the C1B alignment in the northern part of the state is seen as complex because it involves various types of construction in addition to bridges and tunnels.


"I say it is critical because we started this ECRL project in 2017, stopped for a while in July 2018 and resumed in April 2019.


‘’We got approval from the state government for us to implement the ECRL project through the northern line starting December 2021 and we can only start construction work with good cooperation from all state and federal departments and agencies which give us approval in June 2022,’’ the exec said. 


The service is expected to be operational in January 2027 and can accommodate 5.6 million passengers a year aside from also can carry 440 passengers for a trip involving six carriages.



Share This Article

Written By

Jesica Sendai

from 9 to 5 grinder to 'racing' her way in the automotive industry through editorial work.

Share via

JPJ Running Numbers

KUALA LUMPUR

VPY5456

SELANGOR

BSK697

JOHOR

JYK7945

PULAU PINANG

PRV5504

PERAK

APC4203

PAHANG

CFE1146

KEDAH

KGC9254

NEGERI SEMBILAN

NEH5704

KOTA KINABALU

SJN6031

KUCHING

QAB4950M

Last updated 11 Nov, 2025

Fuel Price

Petrol

RON 95

RM 2.60

RON 97

RM 3.20

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 3.02

+0.07

EURO 5 B7

RM 3.22

+0.07

Last updated 06 Nov, 2025

Related News

Auto News
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.

14-10-2025
Auto News
ECRL Project Hits 87% Completion by August 2025 – MoT

ECRL Project Hits 87% Completion by August 2025 – MoT

The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.

23-09-2025
Auto News
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.

24-06-2025
Auto News
ECRL Is More Than 60% Complete - Malaysia Rail

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News
ECRL Project Progress Surpasses 56% - Loke

ECRL Project Progress Surpasses 56% - Loke

ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.

11-12-2023
Auto News
ECRL Kelantan Expected To Be Completed Six Months Earlier

ECRL Kelantan Expected To Be Completed Six Months Earlier

The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.

26-06-2023
Auto News
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.

12-04-2023
Auto News
ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL project's Kuantan Tunnel will be completed by the end of April.

08-03-2023

Latest News

Auto News
PLUS To Close Two Bangi Ramps Nightly Until Nov 28

PLUS To Close Two Bangi Ramps Nightly Until Nov 28

PLUS will close two ramps near Bangi nightly from 10PM to 5AM starting today until Nov 28.

10-11-2025
Auto News
KLIA Aerotrain Halts Daily Midnight To 5am For Maintenance

KLIA Aerotrain Halts Daily Midnight To 5am For Maintenance

KLIA Aerotrain will stop running every night from midnight to 5am for routine checks and maintenance.

10-11-2025
Auto News
4.4 Mil Old Vehicles Threaten Road Safety, Incentive Alone Insufficient

4.4 Mil Old Vehicles Threaten Road Safety, Incentive Alone Insufficient

JPJ data shows over 4.4 million old vehicles are still on the road making up about 17% of the country’s 25.7m active vehicles.

10-11-2025
Auto News
Proton Shifts 15,575 Units In Oct 2025, Outgoing Saga Still Leads

Proton Shifts 15,575 Units In Oct 2025, Outgoing Saga Still Leads

Proton closes Oct 2025 by shifting 15,575 units, outgoing Saga sales spikes to 12-year high ahead of successor’s debut.

10-11-2025
Auto News
JPJ Warns Public Against Fake “Free Driving Licence” TikTok Scams

JPJ Warns Public Against Fake “Free Driving Licence” TikTok Scams

JPJ has warned the public about fake TikTok posts claiming people can get free driving licences without any tests.

10-11-2025
Auto News
RM3b Juru–Sungai Dua Link Cuts Travel Time To Just  20 Minutes

RM3b Juru–Sungai Dua Link Cuts Travel Time To Just 20 Minutes

RM3 billion traffic dispersal project aims to slash travel time between Juru and Sungai Dua from an hour to just 20 minutes.

Auto News
Nanta: Barrier-Free ANPR Toll System Still at RFP Stage

Nanta: Barrier-Free ANPR Toll System Still at RFP Stage

The Works Ministry is inviting proposals for an ANPR-based barrier-free MLFF toll system.

Auto News
New Leapmotor 3S Showroom Opens In Ipoh, Perak

New Leapmotor 3S Showroom Opens In Ipoh, Perak

Perak state capital of Ipoh gains new Leapmotor brand 3S showroom and service outlet operated by dealers CST Auto.

07-11-2025

Show More

trending_flat
Carz Automedia Malaysia Logo
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2025 CariCarz.com. All Rights Reserved.