ECRL Project Progress Surpasses 56% - Loke

Anis

Share via

ECRL-56-Completion-Minister-Loke.jpg

Transport Minister Anthony Loke Siew Fook announced that the East Coast Rail Link (ECRL) project has surpassed 56% of its progress as of November, marking a significant milestone.
This development is in line with the project's completion schedule, which calls for the Gombak Integrated Terminal to be completed by December 2026, and the location of Kota Bharu in Kelantan. By January 2027, operational readiness is expected to be achieved.

Minister Loke stressed the project's transition into a new construction phase, involving flyover beam installations, train station, and depot constructions, highlighting this year as the peak construction phase.

According to The Star, the minister also emphasizes that in order to facilitate passenger and cargo train operations, future stages will concentrate on electrification, signaling, and telecommunication system installations. 03-page-3-chung_2257706_20220325074846-(1).jpg

When it's completed, residents of Kuantan will only need to travel 1.5 hours to get to Kuala Lumpur instead of the three hours it takes now by road. Minister Loke highlighted that 23,000 laborers were involved in 1,900 construction sites, with drill and blast techniques being used to excavate 26 tunnels.

One of the major turning points will be the 16.39 km Genting twin tunnel, which is currently under construction and should be finished in the second quarter of 2025. More than 60km of flyover beams have been installed over the 145km ECRL flyover. The project's overall goal is to improve transportation infrastructure in Pahang, Terengganu, Kelantan, and Selangor by building 20 stations.




Tagged:

ECRL
East Coast Rail Link (ECRL)
ECRL contruction progress
Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

Related News

Auto News

ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.

24-06-2025
Auto News

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News

ECRL Kelantan Expected To Be Completed Six Months Earlier

The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.

26-06-2023
Auto News

"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.

12-04-2023
Auto News

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023
Auto News

ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL project's Kuantan Tunnel will be completed by the end of April.

08-03-2023
Auto News

ECRL Land-Clearing; Enforcement Due To SOP Breach - Selangor MB’s Aide

Selangor Forestry Department found that the alleged land clearing activities in the Selangor State Park are part of the ECRL project.

06-02-2023
Auto News

Kelantan And Terengganu ECRL Project Affected By Floods

The floods last week impacted around 70% of the construction work at sections 1 and 2 of the East Coast Rail Line (ECRL), which spans 82 kilometres from Tunjong here to Setiu in Terengganu.

28-12-2022

Latest News

Auto News

Updated Fuel Prices From 07 To 13 August

The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 07 to 13 August, 2025, the rates are as such.

06-08-2025
Auto News

BYD Zengzhou Carrier Vessel Made Maiden Voyage to Malaysia

BYD’s own Zengzhou carrier vessel just made its maiden voyage to Malaysia, capable of carrying up to 7,000 vehicles.

06-08-2025
Auto News

JPJ Warns Against ‘Kopi-O’ Licences As Fake Driving School Goes Viral

JPJ warns Malaysians against fake “kopi-o licences” offering driving permits without tests or training.

06-08-2025
Auto News

2025 Proton Saga Details Leaked – New 1.5 4-cyl Engine, No MT, Dual-Screens

Alleged details plus snapshots of new 2025 Proton Saga leaks online, new 1.5 4-cyl engine, no MT option, and dual-screens touted.

06-08-2025
Auto News

KKR: MLFF Will Be Privately Funded Under B2B Model

The MLFF toll system will be delivered through a B2B model, with private firms striking direct deals with highway concessionaires.

Auto News

ETS Segamat–Johor Bahru Extension is On Track, No Delays – MoT

Transport Minister Anthony Loke says the ETS extension project from Segamat to Johor Bahru is on track with no delays.

06-08-2025
Auto News

Report: Malaysia Takes Lead in Southeast Asia’s Auto Market

Malaysia for the first time has surpassed Indonesia in quarterly car sales driven by strong local demand.

Auto News

Zero Tolerance Ahead For Untaxed Luxury Cars - Experts

Road safety experts are urging tougher penalties for luxury car owners who skip road tax and insurance.

06-08-2025