LRT3 Will Begin Operations On Sept 30 - Loke

Transport Minister Anthony Loke announced in a parliamentary reply on Wednesday that the Light Rail Transit 3 (LRT3) is scheduled to start operating on September 30 this year.
The 37.8km line connecting Bandar Utama, Petaling Jaya to Johan Setia, Klang, is currently 98.63% complete and expected to be fully completed and handed over to Prasarana Malaysia Bhd by the turnkey contractor by July 31.
In response to Azli Yusof's (Pakatan Harapan-Shah Alam) inquiry about the LRT3 project's current status, including the trial run and expected full operation date, Loke stated that the trial run without passengers will be conducted in two phases to ensure the safety of the LRT3 service. 
According to the minister, the first phase, which will be carried out by the principal contractor, Setia Utama LRT3 Sdn Bhd, will include 75 days of trial run (TR) and fault free run (FFR) from mid-April to late-June 2025. During this period, the Land Public Transport Agency (APAD) will assess the system's safety, compliance, and reliability.
Loke also noted that Rapid Rail Sdn Bhd will conduct a 60-day trial operation under the second phase with technical support from the main contractor. The trial operation, which will run from July to August 2025, will begin after the completion and approval of TR and FFR by APAD. 
The LRT3 project, initially planned with 26 stations and a budget of RM9 billion, saw its cost escalate to RM31.7 billion. In 2018, the Pakatan Harapan administration deferred five stations and cancelled one, reducing the cost to RM16.63 billion. However, in 2024, Prime Minister Anwar Ibrahim announced the reinstatement of the five shelved stations at an additional cost of RM4.7 billion.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VRC3084
SELANGOR
BSQ7494
JOHOR
JYY4834
PULAU PINANG
PSC9624
PERAK
APJ1708
PAHANG
CFG7569
KEDAH
KGG4793
NEGERI SEMBILAN
NEK6349
KOTA KINABALU
SJS3846
KUCHING
QAB9764N
Last updated 17 Jun, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
LRT3 Set for June 2026 Launch, Contractor Faces RM2.73 Million Daily Penalty for Delays
The Shah Alam LRT3 line is targeted to begin operations by June 2026, with contractors liable for RM2.73 million per day in delay penalties.
24-02-2026
LRT3 Shah Alam Line Expected To Open In June
After years of delays, the LRT3 Shah Alam Line could finally begin operations in June, pending final safety tests.
05-02-2026
Prasarana Ridership Jumps 11% in 2025
Prasarana ridership jumps 11% in 2025 hitting 1.31 million users.
07-01-2026
Shah Alam LRT Launch Delayed To Avoid Another 2021 Kelana Jaya Crash
Prasarana delays the Shah Alam LRT opening, prioritising passenger safety and thorough testing after past LRT mishaps.
15-12-2025
LRT3 Won’t Launch This Year As Glitches Persist, No New Date Set
The LRT3 faces another delay after 33 software glitches were discovered during fault-free tests and no new opening date has been fixed yet.
12-12-2025
LRT3 Might Be Delayed Again As Testing Encounters Issues - Report
The LRT3, expected to open early next year, may face further delays due to ongoing signalling system issues.
07-12-2025
Budget 2026: Prasarana Seeks Continued Support for Travel Passes and LRT3
Prasarana moots continued support for travel passes, LRT 3 line completion, cites them as key to easing living costs and improving urban mobility.
09-10-2025
Loke: LRT3 Set To Begin Operations In Q3 2025 - 95.6% Complete
The LRT3 project is currently 95.6% complete and is scheduled to start ferrying passengers by Q3 2025.
29-07-2024
Latest News
It Costs Up To RM300K To Protect One School Zone, And The Government Is Inviting Private Companies To Step Up
Why does a single Safe School Zone cost up to RM300K to build? Transport Minister Anthony Loke breaks down the new physical 30km/h traffic-calming blueprint and why private companies are being asked to step up.
17-06-2026
Prime, Premium, Or Premium Plus? 4 Major Differences Between The 3 Proton e.Mas 7 Tiers
Prime, Premium, or Premium Plus? We break down the 4 massive differences in battery range, price, and luxury features across the new Proton eMas 7 EV tiers.
12-06-2026
15 Drug Records But Still Driving?! Malaysians Are Furious Over The Viral Penang Highway Triton Rampage
Shocking details emerge on the viral Mitsubishi Triton highway crash in Penang. The drugged driver has 17 prior convictions, leaving 18 cars damaged.
10-06-2026
Don't Buy A Car Full Price! Perodua Just Quietly Slashed Prices On 5 Models & The Discounts Vanish After June 30
Perodua just quietly slashed prices on 5 popular models for June 2026! Check out the exact cash rebates for the Myvi, Ativa, Aruz, Bezza, and Axia here.
09-06-2026
Upgraded e.MAS 7 & A Spicy X50?! 5 Things To Check Out At Proton’s KLIMS 2026 Booth This June 12–21
Proton is bringing an upgraded long-range e.MAS 7, a humanoid robot, and new FutureMotion hybrid tech to KLIMS 2026 at MITEC. Here is what to look out for.
09-06-2026
1,400 hp SUV? 3 Wildest Things To See At Zeekr’s KLIMS 2026 Booth This 12-21 June
Looking for ultimate luxury? Discover why you should hold your premium vehicle booking until KLIMS 2026 as Zeekr previews the insane 1,400hp Zeekr 9X PHEV, the 4-seat 009 Grand, and the handle-less 2026 Zeekr X facelift.
09-06-2026
Holding A Showroom Pen? Freeze Your SUV Deposit Until You See Mazda's Booth At KLIMS 2026
Thinking of buying a new SUV? Discover why you should freeze your deposit until KLIMS 2026 as Mazda previews the bigger 3rd-gen Mazda CX-5 and launches the straight-six CX-60 3.3G AWD.
09-06-2026
Heartbreaking Dashcam Footage Reveals Final Moments Before Tragic Collision That Wiped Out 3 Generations Of A Family
A brand-new Proton X50 turned into a nightmare just hours after delivery, as a tragic head-on collision claimed the lives of 6 family members, including a baby.
08-06-2026
Show More
trending_flat