LRT3 Will Begin Operations On Sept 30 - Loke

Anis

Share via

230705-LRT3-MRT-LRT-map.jpg


Transport Minister Anthony Loke announced in a parliamentary reply on Wednesday that the Light Rail Transit 3 (LRT3) is scheduled to start operating on September 30 this year.

The 37.8km line connecting Bandar Utama, Petaling Jaya to Johan Setia, Klang, is currently 98.63% complete and expected to be fully completed and handed over to Prasarana Malaysia Bhd by the turnkey contractor by July 31.

In response to Azli Yusof's (Pakatan Harapan-Shah Alam) inquiry about the LRT3 project's current status, including the trial run and expected full operation date, Loke stated that the trial run without passengers will be conducted in two phases to ensure the safety of the LRT3 service.
lrt-3-train-5-e1624335707437.jpg


According to the minister, the first phase, which will be carried out by the principal contractor, Setia Utama LRT3 Sdn Bhd, will include 75 days of trial run (TR) and fault free run (FFR) from mid-April to late-June 2025. During this period, the Land Public Transport Agency (APAD) will assess the system's safety, compliance, and reliability.

Loke also noted that Rapid Rail Sdn Bhd will conduct a 60-day trial operation under the second phase with technical support from the main contractor. The trial operation, which will run from July to August 2025, will begin after the completion and approval of TR and FFR by APAD.
3002622.jpg


The LRT3 project, initially planned with 26 stations and a budget of RM9 billion, saw its cost escalate to RM31.7 billion. In 2018, the Pakatan Harapan administration deferred five stations and cancelled one, reducing the cost to RM16.63 billion. However, in 2024, Prime Minister Anwar Ibrahim announced the reinstatement of the five shelved stations at an additional cost of RM4.7 billion.

Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

JPJ Running Numbers

KUALA LUMPUR

VPG4263

SELANGOR

BSF5053

JOHOR

JYA4985

PULAU PINANG

PRR4956

PERAK

ANW6749

PAHANG

CFC1439

KEDAH

KGA9426

NEGERI SEMBILAN

NEG2387

KOTA KINABALU

SJL3071

KUCHING

QAB5149L

Last updated 17 Jun, 2025

Fuel Price

Petrol

RON 95

RM 2.05

RON 97

RM 3.07

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 2.74

EURO 5 B7

RM 2.94

Last updated 12 Jun, 2025

Related News

Auto News

Loke: LRT3 Set To Begin Operations In Q3 2025 - 95.6% Complete

The LRT3 project is currently 95.6% complete and is scheduled to start ferrying passengers by Q3 2025.

29-07-2024
Auto News

LRT3: Intermittent Road Closure On PLUS & SPRINT from July 2 to Sept 30

A series of intermittent road closures will take place on PLUS and SPRINT highways from July 2 to Sept 30 for LRT3 construction works.

27-06-2024
Auto News

LRT 3: Subang Airport Road, Lane Closure & Road Diversion - 16 Sept To 31 Dec 2023

Lane closures and traffic diversions on Subang Airport Road in both the Subang and Kuala Lumpur directions will be extended for the LRT3 works

12-09-2023
Auto News

LRT 3: NKVE Intermittent Lane Closure, KM14.9 To KM16.2 From 26 Aug - 28 Aug

LRT3 would carry out intermittent lane closures and traffic diversions on NKVE between KM14.9 and KM16.2 (for both Kuala Lumpur/Sungai Buloh and Shah Alam/Subang-bound lanes).

24-08-2023
Auto News

LOKE : LRT3 86% Complete, To Begin Service 1 March 2025 - 67,000 Daily Capacity

Light Rail Transit 3 (LRT3) project 86% complete - Service to begin on 1 March, 2025

05-07-2023
Auto News

LRT3: Intermittent Road Closure On PLUS & SPRINT from July 2 to Sept 30

A series of intermittent road closures will take place on PLUS and SPRINT highways from July 2 to Sept 30 for LRT3 construction works.

27-06-2024
Auto News

Loke: KEJARA System A Failure, Major Revamp Coming

KEJARA system has failed to penalise traffic offenders who ignore their summonses, admits Loke.

13-06-2025
Auto News

New Speed Limit Device Mandatory In Heavy Vehicles Starting Oct 2025

Speed Limitation Device (SLD) will be compulsory for commercial vehicles starting Oct 2025 to meet national road safety targets.

13-06-2025

Latest News

Auto News

Amir Hamzah: RON95 Subsidy Coming Reform Before 2026 Carbon Tax

RON95 petrol subsidies to be rationalised ahead of 2026 carbon tax rollout, comes as part of Malaysia’s energy transition.

17-06-2025
Auto News

Malaysian Single-Mom Truckers Make Local Headlines

In a male-dominated industry, 39-year-old Irzunika Idris and 40-year-old Marlia Ramli became truck drivers to support their kids.

17-06-2025
Auto News

Rapid KL On-Demand Adds 5 New Zones — Cyberjaya & Putrajaya Included

The Rapid KL On-Demand service has been expanded to five new zones, including Cyberjaya and Putrajaya.

17-06-2025
Auto News

PRO-NET Opens Three New Proton e.MAS & smart Dealerships

PRO-NET has expanded both its Proton e.MAS and smart dealer network by opening three new outlets in Malaysia.

17-06-2025
Auto News

FT Dept, JPJ Told To Deal With Abandoned Vehicles

FT Dept and JPJ ordered to review and improve laws on abandoned vehicle disposal in KL and Putrajaya.

17-06-2025
Auto News

Gerik Crash: PSV Licence Suspended, RM1.7M Aid Raised

JPJ suspends Gerik crash bus driver’s PSV licence as investigations rule out technical failure.

17-06-2025
Auto News

PLUS Opens Three New Lanes At Rawang Selatan Toll Plaza

PLUS has announced the addition of three new lanes at the Rawang Selatan toll plaza (Exit 115).

16-06-2025
Auto News

RON95 Petrol Subsidy Rationalisation Will Proceed – PMX

The government will proceed with the RON95 fuel subsidy rationalisation, says Prime Minister Anwar Ibrahim.

16-06-2025

Show More

trending_flat
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2025 CariCarz.com. All Rights Reserved.