LRT3 Will Begin Operations On Sept 30 - Loke

Anis

Share via

230705-LRT3-MRT-LRT-map.jpg


Transport Minister Anthony Loke announced in a parliamentary reply on Wednesday that the Light Rail Transit 3 (LRT3) is scheduled to start operating on September 30 this year.

The 37.8km line connecting Bandar Utama, Petaling Jaya to Johan Setia, Klang, is currently 98.63% complete and expected to be fully completed and handed over to Prasarana Malaysia Bhd by the turnkey contractor by July 31.

In response to Azli Yusof's (Pakatan Harapan-Shah Alam) inquiry about the LRT3 project's current status, including the trial run and expected full operation date, Loke stated that the trial run without passengers will be conducted in two phases to ensure the safety of the LRT3 service.
lrt-3-train-5-e1624335707437.jpg


According to the minister, the first phase, which will be carried out by the principal contractor, Setia Utama LRT3 Sdn Bhd, will include 75 days of trial run (TR) and fault free run (FFR) from mid-April to late-June 2025. During this period, the Land Public Transport Agency (APAD) will assess the system's safety, compliance, and reliability.

Loke also noted that Rapid Rail Sdn Bhd will conduct a 60-day trial operation under the second phase with technical support from the main contractor. The trial operation, which will run from July to August 2025, will begin after the completion and approval of TR and FFR by APAD.
3002622.jpg


The LRT3 project, initially planned with 26 stations and a budget of RM9 billion, saw its cost escalate to RM31.7 billion. In 2018, the Pakatan Harapan administration deferred five stations and cancelled one, reducing the cost to RM16.63 billion. However, in 2024, Prime Minister Anwar Ibrahim announced the reinstatement of the five shelved stations at an additional cost of RM4.7 billion.

Share This Article

Written By

Anis

Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........

Share via

JPJ Running Numbers

KUALA LUMPUR

VPM4900

SELANGOR

BSG7498

JOHOR

JYE4605

PULAU PINANG

PRT744

PERAK

ANY6854

PAHANG

CFD479

KEDAH

KGB6308

NEGERI SEMBILAN

NEG6323

KOTA KINABALU

SJL9999*

KUCHING

QAB8364L

Last updated 03 Aug, 2025

Fuel Price

Petrol

RON 95

RM 2.05

RON 97

RM 3.17

-0.04

RON 100

RM 5.00

VPR

RM 6.23

Diesel

EURO 5 B10

RM 2.91

EURO 5 B7

RM 3.11

Last updated 31 Jul, 2025

Related News

Auto News

Loke: LRT3 Set To Begin Operations In Q3 2025 - 95.6% Complete

The LRT3 project is currently 95.6% complete and is scheduled to start ferrying passengers by Q3 2025.

Auto News

LRT3: Intermittent Road Closure On PLUS & SPRINT from July 2 to Sept 30

A series of intermittent road closures will take place on PLUS and SPRINT highways from July 2 to Sept 30 for LRT3 construction works.

Auto News

LRT 3: Subang Airport Road, Lane Closure & Road Diversion - 16 Sept To 31 Dec 2023

Lane closures and traffic diversions on Subang Airport Road in both the Subang and Kuala Lumpur directions will be extended for the LRT3 works

Auto News

LRT 3: NKVE Intermittent Lane Closure, KM14.9 To KM16.2 From 26 Aug - 28 Aug

LRT3 would carry out intermittent lane closures and traffic diversions on NKVE between KM14.9 and KM16.2 (for both Kuala Lumpur/Sungai Buloh and Shah Alam/Subang-bound lanes).

Auto News

LOKE : LRT3 86% Complete, To Begin Service 1 March 2025 - 67,000 Daily Capacity

Light Rail Transit 3 (LRT3) project 86% complete - Service to begin on 1 March, 2025

Auto News

LRT3: Intermittent Road Closure On PLUS & SPRINT from July 2 to Sept 30

A series of intermittent road closures will take place on PLUS and SPRINT highways from July 2 to Sept 30 for LRT3 construction works.

Auto News

LRT3 Hits 99% Completion - Loke

LRT3, which will connect Bandar Utama to Johan Setia, is 99% complete and on track for launch, says Transport Minister.

30-07-2025
Auto News

Bas.My Launched with Focus on Accessibility and Affordability

Loke: 48 brand-new buses and 13 routes, Bas.My is setting a new standards for stage buses in Kedah.

Latest News

Auto News

JPJ: RM3 Million Rolls-Royce Among 53 Vehicles Seized

JPJ Ops Luxury 2.0 sees 53 high-end vehicles, including a Rolls-Royce Cullinan and Lamborghini Huracan, seized over expired road tax and insurance.

Auto News

Malaysian-Bound Toyota Yaris Cross Receives 5-Star ASEAN NCAP Score

The DNGA-based Toyota Yaris Cross just received a five-star score for the ASEAN NCAP crash test. Coming to Malaysia soon?

02-08-2025
Auto News

Chery’s Lepas Brand Entering Malaysia Soon? ‘Official’ IG Page Sighted

New ‘official’ IG page we sighted by chance indicates Chery’s new Lepas sub-brand is set to enter Malaysia very soon.

01-08-2025
Auto News

Govt Looking To Revive MEX II Highway With New Completion Plan

The government is working with bondholders to restart the long-delayed MEX II Highway.

01-08-2025
Auto News

2025 Proton X50 Facelift Sees 999 Units Shifted In 5 Days

2025 Proton X50 Facelift sees 999 units delivered in just five days, production hits 2,000 units mark as of end of July too.

01-08-2025
Auto News

Bridgestone Turanza 6 Tyres Launched in Malaysia – 14 to 21 Inches, EV-Ready

Bridgestone Malaysia has introduced the new Turanza 6 tyres in Malaysia, with sizes ranging from 14 to 21 inches.

01-08-2025
Auto News

Johor Proposes RTS2 Link Between Iskandar Puteri and Tuas

With Bukit Chagar terminal nearing completion, Johor eyes new RTS2 link to Tuas to further ease cross-border travel.

Auto News

PAC to KKR: Avoid Costly Missteps in Delayed MLFF Rollout

PAC wants KKR to ensure no hidden costs to government or road users in the upcoming MLFF toll system rollout.

Show More

trending_flat
About Us

CarzAutoMedia: Stay connected to the latest car news! Get instant updates on new releases, industry trends, and automotive innovations. Your go-to source for 24/7 coverage of everything automotive.

© 2025 CariCarz.com. All Rights Reserved.