ECRL Kelantan LIne 87.8% Complete, On Track for 2026 Completion
KS
16-1-2025
Malaysia Rail Link (MRL) CEO Datuk Seri Darwis Abdul Razak announced that the 400 KM East Coast Rail Link (ECRL) track installation from Maran, Pahang, to Kota Bharu, Kelantan, has been completed ahead of schedule by two and a half months.
For the first time in Malaysia, the CCPG-500A track-laying machine was used to lay 206 KM of tracks from Dungun, Terengganu, to Kota Bharu, Kelantan. The machine successfully completed its work at Kota Bharu Station, which will also serve as the starting point of the ECRL line.
As of Dec 2024, the ECRL project in Kelantan is 87.8% complete. This progress will help speed up the installation of electrification, signaling, and telecommunications for the remaining 43.86KM stretch in the state.
The Kelantan section includes two stations: Kota Bharu Station (for passengers) and Pasir Puteh Station (for both passengers and cargo). Both stations are expected to be completed by the second quarter of 2026.
The full 665KM ECRL line will connect Kelantan, Terengganu, and Pahang on the East Coast to Selangor on the West Coast. The project is expected to be finished by Dec 2026, with operations starting in Jan 2027. Once complete, this line is expected to boost regional economic growth and transform Malaysia’s rail network.
On ticket prices, Darwis assured that fares will be affordable, with more details to be announced by the Transport Ministry.
Written By
KS
More then half his life spend being obsessed with all thing go-fast, performance and automotive only to find out he's actually Captain Slow behind the wheels...oh well! https://www.linkedin.com/in/kumeran-sagathevan/
JPJ Running Numbers
KUALA LUMPUR
VPD3957
SELANGOR
BSE7452
JOHOR
JXX4674
PULAU PINANG
PRQ6532
PERAK
ANV7298
PAHANG
CFB7647
KEDAH
KGA5811
NEGERI SEMBILAN
NEF8764
KOTA KINABALU
SJK9417
KUCHING
QAB3616L
Last updated 19 May, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.07
-0.03
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.77
-0.03
EURO 5 B7
RM 2.97
-0.03
Last updated 15 May, 2025
Related News
Thai Ambassador Proposes ECRL Extension To Sungai Golok
Thai Ambassador Lada Phumas suggested extending the ECRL to Sungai Golok for better rail links.
16-05-2025
ECRL Hits 82% Completion, Promises 1,800 Jobs - 80% For Locals
ECRL, Malaysia’s largest rail project is nearing completion, with passenger service set to begin by Jan 2027.
06-05-2025
ECRL to Boost East Coast Growth, Strengthen Malaysia-China Ties
The ECRL project is set to unlock new growth for Malaysia’s east coast and strengthen links with China.
29-04-2025
ECRL Railway Construction Along Kota Bharu-Selangor Over 80% Complete
ECRL project along Kota Bharu-Selangor alignment is over 81% complete and remains on track for completion in Dec 2026.
18-04-2025
ECRL Concludes 38 Tunnel Excavations Ahead Of Schedule
MRL announces the completion of excavation work for 38 tunnels along the ECRL rail line.
09-04-2025
ECRL 80% Complete, Shifting To Above-Ground Work
The ECRL project, which is nearing 80% completion, is transitioning from the underground construction phase to above-ground work.
27-03-2025
MOT Developing Policy To Encourage Cargo Companies To Use ECRL
MOT will implement a policy to incentivize the industry to use the ECRL service.
06-03-2025
ECRL: Port Klang Stretch Will Be Upgraded to Double-Track System
The 25-KM stretch of the ECRL at Port Klang will be upgraded to a double-track system with no extra cost, MOT says.
18-02-2025
Latest News
Lack Of First- And Last-Mile Connectivity Limits Public Transport Ridership - Experts
Experts state that inadequate first- and last-mile connectivity limits public transport ridership, leading people to prefer their cars.
19-05-2025
Foreign Driving License Conversions To Cease On May 19 - JPJ
JPJ is no longer processing requests to switch foreign driver's licenses to Malaysian licenses starting today (May 19).
19-05-2025
TrackScore and MIRA Unveiled as MIROS Advances Road Safety Agenda
MIROS introduces MIRA and TrackScore safety assessment programs, signs three industry agreements to enhance road safety in Malaysia.
19-05-2025
Rapid KL Bus Lane Hours Extended — Now From 4.30 PM to 7 PM
Rapid KL has extended the operating hours of its bus lane in Jalan Ampang, now going from 4.30 PM to 7 PM.
16-05-2025
Eurorepar Multi-brand Service And Repair By Stellantis Entering Malaysia Soon
Stellantis set to introduce Eurorepar aftermarket multi-brand service and repair banner in Malaysia soon.
16-05-2025
NIOSH Ready To Train Heavy Vehicle Drivers To Prevent Accidents
NIOSH is ready to train heavy vehicle drivers using a specialized SDDP module to prevent accidents.
16-05-2025
Thai Ambassador Proposes ECRL Extension To Sungai Golok
Thai Ambassador Lada Phumas suggested extending the ECRL to Sungai Golok for better rail links.
16-05-2025
Proton Xchange Programme Launched To Woo Older Car Owners To Trade-in And Up
New Proton Xchange Programme sees national automaker wooing older car owners to trade-in and up.
15-05-2025
Show More
trending_flat