LRT3 Won’t Launch This Year As Glitches Persist, No New Date Set
The LRT3 Shah Alam Line will not open this year, with Prasarana confirming that the line failed to complete its fault-free run (FFR) due to multiple software issues.
Prasarana officials said 33 glitches were detected during FFR tests that began on Aug 26, 2025. These included problems with train docking, door functions, trains failing to depart stations, and false speed or stopping alarms.
"Because these faults surfaced during mandatory testing, the main contractor, Setia Utama LRT 3 Sdn Bhd, will not face penalties," Prasarana CEO Amir Hamdan said.
.jpg)
For approval, the first train must complete 4,000km fault-free while other trains must each cover 2,500km. So far, the first train has met its requirement, and three others have surpassed 3,000km.
"The delay will not incur extra government costs as the project uses a fixed-price contract. All testing is expected to be completed by the end of Jan, with a new launch date to be announced next month," he added.
.jpg)
.jpg)
He further noted that the project timeline remains aligned with the Transport Ministry’s expectations, although unforeseen software issues caused the missed December 2025 deadline.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQD3506
SELANGOR
BSK7637
JOHOR
JYM6385
PULAU PINANG
PRW4944
PERAK
APD3031
PAHANG
CFE4268
KEDAH
KGD4043
NEGERI SEMBILAN
NEH8594
KOTA KINABALU
SJP2493
KUCHING
QAB7320M
Last updated 12 Dec, 2025
Fuel Price
Petrol
RON 95
RM 2.64
-0.02
RON 97
RM 3.27
-0.02
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.06
-0.02
EURO 5 B7
RM 3.26
-0.02
Last updated 11 Dec, 2025
Related News
LRT3 Might Be Delayed Again As Testing Encounters Issues - Report
The LRT3, expected to open early next year, may face further delays due to ongoing signalling system issues.
07-12-2025
Budget 2026: Prasarana Seeks Continued Support for Travel Passes and LRT3
Prasarana moots continued support for travel passes, LRT 3 line completion, cites them as key to easing living costs and improving urban mobility.
09-10-2025
LRT3 Will Begin Operations On Sept 30 - Loke
LRT3 will begin operating on September 30 this year, Transport Minister Anthony Loke announced.
27-02-2025
Loke: LRT3 Set To Begin Operations In Q3 2025 - 95.6% Complete
The LRT3 project is currently 95.6% complete and is scheduled to start ferrying passengers by Q3 2025.
29-07-2024
LRT3: Intermittent Road Closure On PLUS & SPRINT from July 2 to Sept 30
A series of intermittent road closures will take place on PLUS and SPRINT highways from July 2 to Sept 30 for LRT3 construction works.
27-06-2024
LRT 3: Subang Airport Road, Lane Closure & Road Diversion - 16 Sept To 31 Dec 2023
Lane closures and traffic diversions on Subang Airport Road in both the Subang and Kuala Lumpur directions will be extended for the LRT3 works
12-09-2023
LRT 3: NKVE Intermittent Lane Closure, KM14.9 To KM16.2 From 26 Aug - 28 Aug
LRT3 would carry out intermittent lane closures and traffic diversions on NKVE between KM14.9 and KM16.2 (for both Kuala Lumpur/Sungai Buloh and Shah Alam/Subang-bound lanes).
24-08-2023
LOKE : LRT3 86% Complete, To Begin Service 1 March 2025 - 67,000 Daily Capacity
Light Rail Transit 3 (LRT3) project 86% complete - Service to begin on 1 March, 2025
05-07-2023
Latest News
Gemas-JB Electrified Train Cuts KL-Johor Travel To 4 Hours
The new electrified Gemas-Johor Bahru train line slashes travel time from KL to Johor to just 4 hours 20 minutes.
12-12-2025
PLUS and KEC Ink MoU to Advance Smart Mobility
PLUS and KEC Smart Mobility signs agreement to develop smarter, greener and more connected expressway operations.
12-12-2025
LRT3 Won’t Launch This Year As Glitches Persist, No New Date Set
The LRT3 faces another delay after 33 software glitches were discovered during fault-free tests and no new opening date has been fixed yet.
12-12-2025
CKD GWM WEY G9 Rolls Out at New EPMB Plant
CKD GWM WEY G9 rolls out from EPMB’s new Phase 2 plant, strengthening Malaysia’s NEV localisation ecosystem.
12-12-2025
Proton Shifts 13,451 Units Throughout Nov 2025
Proton closes Nov 2025 by shifting 13,451 units, touts to be “on target” for record exports growth too.
11-12-2025
EV9, Carnival & Sportage Set To Kick-Start Local Kia Brand Revival
Newly formed Kia Sales Malaysia (KSM) principal-led entity set to reboot brand locally with EV9, Carnival and Sportage models first.
11-12-2025
Nov 2025 Vehicle Reg Down 4.4% MoM, xEV Edges Up 10.3%
Vehicle registration held firm in Nov, with xEVs inching up to 10.3% despite a 4.4% dip in overall sales.
11-12-2025
Updated Fuel Prices From 11 To 17 December
The Ministry of Finance (MoF) has announced the retail prices of all fuels in Malaysia, for the coming week of 11 to 17 December, 2025, the rates are as such.
10-12-2025
Show More
trending_flat