LRT3 Won’t Launch This Year As Glitches Persist, No New Date Set
The LRT3 Shah Alam Line will not open this year, with Prasarana confirming that the line failed to complete its fault-free run (FFR) due to multiple software issues.
Prasarana officials said 33 glitches were detected during FFR tests that began on Aug 26, 2025. These included problems with train docking, door functions, trains failing to depart stations, and false speed or stopping alarms.
"Because these faults surfaced during mandatory testing, the main contractor, Setia Utama LRT 3 Sdn Bhd, will not face penalties," Prasarana CEO Amir Hamdan said.
.jpg)
For approval, the first train must complete 4,000km fault-free while other trains must each cover 2,500km. So far, the first train has met its requirement, and three others have surpassed 3,000km.
"The delay will not incur extra government costs as the project uses a fixed-price contract. All testing is expected to be completed by the end of Jan, with a new launch date to be announced next month," he added.
.jpg)
.jpg)
He further noted that the project timeline remains aligned with the Transport Ministry’s expectations, although unforeseen software issues caused the missed December 2025 deadline.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VQQ9557
SELANGOR
BSN4490
JOHOR
JYT4137
PULAU PINANG
PSA6256
PERAK
APG967
PAHANG
CFF8337
KEDAH
KGE8161
NEGERI SEMBILAN
NEJ8037
KOTA KINABALU
SJQ8463
KUCHING
QAB4203N
Last updated 19 Mar, 2026
Fuel Price
Petrol
RON 95
RM 2.59
+0.05
RON 97
RM 3.15
+0.05
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 3.04
+0.05
EURO 5 B7
RM 3.24
+0.05
Last updated 26 Feb, 2026
Related News
Prasarana to Reveal LRT3 Launch Date This April—Here’s Everything We Know So Far
The wait for the LRT3 Shah Alam Line is entering its final stretch. After months of "will they, won't they" speculation, Prasarana has officially pointed to April 2026 as the month of truth.
05-03-2026
Latest News
From 82 Minutes to 8: How the Mutiara Line is Giving Penangites Their Time Back
Is the 80-minute Penang Bridge crawl finally ending? The Mutiara Line LRT links Butterworth to Komtar in just 8 minutes. Get the latest 2026 project updates, station lists, and more.
17-03-2026
The 2026 Proton X90 Buyer’s Warning: 5 Critical Safety Features You Are No Longer Getting
ASEAN NCAP revokes Proton X90’s 5-star rating. The 2026 facelift is downgraded to 1-star after stripping critical ADAS features. Is your family safe? Get the full safety specs here.
16-03-2026
9,000+ Drivers Chose Toyota Hybrids This Year: Proof That Toyota’s Multi-Pathway Strategy Works
Toyota Malaysia hits 9,556 sales in early 2026, proving the "Multi-Pathway" strategy works. From Vios Hybrid to Vellfire HEV, see why hybrids are winning the sales war.
12-03-2026
Chery Tiggo 7 is Now the Safest Chinese SUV on the Planet, This Is Why
The Chery Tiggo 7 makes history as the only Chinese SUV to sweep 5-star ratings from Euro NCAP, ANCAP, and ASEAN NCAP. With a record 94.68 points, see why this is 2026’s safest family SUV.
11-03-2026
Sepang Dates Confirmed: Catch Team Porsche Malaysia in Action on 21–23 August
While the 2026 Porsche Carrera Cup Asia (PCCA) season kicks off in Shanghai this weekend, Malaysian fans are already looking ahead to the highlight of the year: the homecoming.
10-03-2026
Iran-US War Day 10: It’s Not Just Fuel — Malaysia’s Automotive Industry Faces New Risks
While the BUDI95 subsidy program is already feeling the heat of oil prices flirting with US$120 a barrel, the true threat to our automotive sector lies beneath the surface.
09-03-2026
Prasarana to Reveal LRT3 Launch Date This April—Here’s Everything We Know So Far
The wait for the LRT3 Shah Alam Line is entering its final stretch. After months of "will they, won't they" speculation, Prasarana has officially pointed to April 2026 as the month of truth.
05-03-2026
EV King is Here: How Proton e.MAS 5 Dethroned Popular Petrol Cars in 60 Days
PRO-NET has announced that the Proton e.MAS 5 has officially surpassed the 5,000-unit delivery milestone in just two months.
05-03-2026
Show More
trending_flat