The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.

The East Coast Rail Link (ECRL) project spanning Kelantan, Terengganu, Pahang, and Selangor has recorded an overall completion of 87% as of August this year, said Transport Minister Anthony Loke.

As reported by Bernama, the minister said the project segment in Terengganu is among the fastest to be completed, as land issues were resolved earlier, coupled with its overall flat geographical terrain, thus possessing fewer construction challenges.

548195012_1374359560713294_6709422170773546027_n.jpg

Transport Minister YB Anthony Loke

“In Terengganu, track works are almost completed. The only sections yet to be finished are from Bentong to Gombak, particularly the Genting tunnel up to Gombak, which is the most challenging segment,” Loke told reporters after officiating the BAS.MY Kuala Terengganu Service Transformation Programme yesterday.

ECRL_PASIR_PUTEH_1755593670.jpgECRL_Paka_tunnel7_09042021.jpg

That said, the minister continued that progress in both Kelantan and Terengganu remains on track, as most of the major construction works there have been completed. However, he revealed that incidents of cable theft in Pahang have disrupted the work progress in the state.

“More than a kilometre of cables was stolen, which created problems for the developer. They now have to review their approach to accelerate progress.

“I have already discussed this with the Home Ministry and the police. More aggressive action is needed, including enforcing stricter laws to curb this issue,” Loke added.

Apart from causing delays and heavy losses, the minister also pointed out that cable thefts pose high risks to public safety.

ECRL-Map.jpg

Back to the ECRL project, the first phase from Kota Bharu to Gombak is scheduled for completion in December 2026, with first testing and certification set to take place earlier in June 2026. Meanwhile, the second phase, from Gombak to Port Klang, is scheduled to be completed later in December 2027, with the full operations expected to begin in Jan 2028.

Source: Bernama


Gallery

Tagged:

ECRL
East Coast Rail Link (ECRL)
ECRL project
Transport Minister YB Anthony Loke
ECRL Construction Progress
Share This Article

Written By

Mukhlis Azman

An avid two-wheeler that writes and talks about four-wheelers for a living, while dreaming of an urban transit-laden Malaysia. @mukhlisazman

Share via

Related News

Auto News

ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.

24-06-2025
Auto News

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News

ECRL Project Progress Surpasses 56% - Loke

ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.

11-12-2023
Auto News

ECRL Kelantan Expected To Be Completed Six Months Earlier

The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.

26-06-2023
Auto News

"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.

12-04-2023
Auto News

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023
Auto News

ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL project's Kuantan Tunnel will be completed by the end of April.

08-03-2023
Auto News

ECRL Land-Clearing; Enforcement Due To SOP Breach - Selangor MB’s Aide

Selangor Forestry Department found that the alleged land clearing activities in the Selangor State Park are part of the ECRL project.

06-02-2023

Latest News

Auto News

Slowing Car Sales May Spark Price War - Analysts

Analysts warn 2025’s weaker auto market may spark intense price cuts, making now a great time for buyers to grab deals.

24-09-2025
Auto News

Five Major Roads to Close for Sultan of Selangor Cup 2025

Five major roads in KL will close on Sept 27 from 2 pm for the Sultan of Selangor Cup.

24-09-2025
Auto News

Budi95: Malaysians Save Up to RM228 Monthly, Govt Up to RM4 Billion

Budi95 will see Malaysians save up to RM228 per month, while the government trims RM2.5–4 billion off subsidy costs.

Auto News

Nilai Auto City: N. Sembilan’s RM1 Billion Leap into the Automotive Map

RM1 billion Auto City project at Nilai Smart City aims to turn the region into a leading automotive hub.

Auto News

Amir Hamzah: No Daily Refuel Limits Under Budi95 For Now

Amir Hamzah: No limit on daily refuels, data analytics to monitor RM1.99 subsidy use to detect abuse.

Auto News

New RM22.7M JPJ Kajang Office Set for 2027

The new RM22.7M JPJ Kajang office will feature modern facilities and improved services for the public by 2027.

23-09-2025
Auto News

ECRL Project Hits 87% Completion by August 2025 – MoT

The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.

23-09-2025
Auto News

Amir Hamzah: No Back-to-Back Pumping of RM1.99 RON95 A Day

Amir Hamzah: Govt. won't allow multiple subsidised refuels in a day as BUDI95 takes effect Sept 30.