ECRL Project Hits 87% Completion by August 2025 – MoT

Mukhlis Azman

Share via

ecrl-genting-.jpgph06-19062024-ecrl_4279690_20240619165601.jpg

The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.

The East Coast Rail Link (ECRL) project spanning Kelantan, Terengganu, Pahang, and Selangor has recorded an overall completion of 87% as of August this year, said Transport Minister Anthony Loke.

As reported by Bernama, the minister said the project segment in Terengganu is among the fastest to be completed, as land issues were resolved earlier, coupled with its overall flat geographical terrain, thus possessing fewer construction challenges.

548195012_1374359560713294_6709422170773546027_n.jpg

Transport Minister YB Anthony Loke

“In Terengganu, track works are almost completed. The only sections yet to be finished are from Bentong to Gombak, particularly the Genting tunnel up to Gombak, which is the most challenging segment,” Loke told reporters after officiating the BAS.MY Kuala Terengganu Service Transformation Programme yesterday.

ECRL_PASIR_PUTEH_1755593670.jpgECRL_Paka_tunnel7_09042021.jpg

That said, the minister continued that progress in both Kelantan and Terengganu remains on track, as most of the major construction works there have been completed. However, he revealed that incidents of cable theft in Pahang have disrupted the work progress in the state.

“More than a kilometre of cables was stolen, which created problems for the developer. They now have to review their approach to accelerate progress.

“I have already discussed this with the Home Ministry and the police. More aggressive action is needed, including enforcing stricter laws to curb this issue,” Loke added.

Apart from causing delays and heavy losses, the minister also pointed out that cable thefts pose high risks to public safety.

ECRL-Map.jpg

Back to the ECRL project, the first phase from Kota Bharu to Gombak is scheduled for completion in December 2026, with first testing and certification set to take place earlier in June 2026. Meanwhile, the second phase, from Gombak to Port Klang, is scheduled to be completed later in December 2027, with the full operations expected to begin in Jan 2028.

Source: Bernama


Gallery

Tagged:

ECRL
East Coast Rail Link (ECRL)
ECRL project
Transport Minister YB Anthony Loke
ECRL construction progress
Share This Article

Written By

Mukhlis Azman

An avid two-wheeler that writes and talks about four-wheelers for a living, while dreaming of an urban transit-laden Malaysia. @mukhlisazman

Share via

Related News

Auto News

ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses

The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.

14-10-2025
Auto News

ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO

MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.

24-06-2025
Auto News

ECRL Is More Than 60% Complete - Malaysia Rail

ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.

25-03-2024
Auto News

ECRL Project Progress Surpasses 56% - Loke

ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.

11-12-2023
Auto News

ECRL Kelantan Expected To Be Completed Six Months Earlier

The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.

26-06-2023
Auto News

"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke

The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.

12-04-2023
Auto News

ECRL Project In Terengganu Reaches 55% Progress

The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.

05-04-2023
Auto News

ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%

ECRL project's Kuantan Tunnel will be completed by the end of April.

08-03-2023

Latest News

Auto News

LATAR Interchange Opens, Direct Access To Eco Grandeur

The Eco Grandeur Interchange and Toll Plaza has officially opened, offering direct access through Exit 2502 to Eco Grandeur.

11-11-2025
Auto News

Penang Sentral Set to Become Mainland’s Integrated Transport Hub

The Butterworth KTM station, Mutiara Line LRT, and airport expansions will turn Penang Sentral into key transport and logistics hub.

Auto News

Six Bidders Eye Barrier-Free MLFF Toll System - Report

Six consortiums are reportedly competing to roll out Malaysia’s long-awaited MLFF toll system.

11-11-2025
Auto News

EV Ownership Risky, Battery Leasing Could Ease Depreciation Risks - Analysts

EVs can lose nearly half their value in five years, while high battery costs and limited infrastructure keep ownership risky.

11-11-2025
Auto News

PLUS To Close Two Bangi Ramps Nightly Until Nov 28

PLUS will close two ramps near Bangi nightly from 10PM to 5AM starting today until Nov 28.

10-11-2025
Auto News

KLIA Aerotrain Halts Daily Midnight To 5am For Maintenance

KLIA Aerotrain will stop running every night from midnight to 5am for routine checks and maintenance.

10-11-2025
Auto News

4.4 Mil Old Vehicles Threaten Road Safety, Incentive Alone Insufficient

JPJ data shows over 4.4 million old vehicles are still on the road making up about 17% of the country’s 25.7m active vehicles.

10-11-2025
Auto News

JPJ Warns Public Against Fake “Free Driving Licence” TikTok Scams

JPJ has warned the public about fake TikTok posts claiming people can get free driving licences without any tests.

10-11-2025