ECRL Land-Clearing; Enforcement Due To SOP Breach - Selangor MB’s Aide
According to state government staffer Jay Jay Denis, a Chinese construction company responsible for clearing land in Selangor's forest reserves for the East Coast Rail Link (ECRL) project was subject to enforcement action last year for failing to follow standard operating procedures.
Despite having a permit to work on the ECRL, China Communications Construction Company (M) Sdn Bhd (CCCC) started construction on that part of the project in Selangor in December of last year before getting the go-ahead from the state Forestry Department.
"They (CCCC) believed they could start working right away because they had the permit, but they actually needed to apply to the department to let authorities know they would be beginning work.
When contacted, he explained, "This is so that the department can send personnel to the site to ensure that the proper parts of the forests are being carved out."
The stop-work order and fine that were imposed on the company in December have since been lifted, according to the special officer to Selangor Menteri Besar Datuk Seri Amirudin Shari. "The company was informed in December that they will need to follow the proper administrative procedures in order to start working in the future.
The problem back then was simply that they failed to give a notice (to the department), he said. "If (CCCC) had no permit to operate then, there would definitely have been further legal action," he said.
Denis' remarks follow yesterday's statement by state executive councillor Hee Loy Sian that a use permit had been issued by the department in July 2022 for the execution of the ECRL project in the permanent forest reserve area.
The head of the state's Environment, Green Technology, Tourism, and Orang Asli Affairs Committee also stated that on November 30, 2021, Malaysia Rail Link Sdn Bhd, the department of the Finance Ministry in charge of managing the ECRL project, received approval for the environmental impact assessment report for Section C2 (Gombak-Serendah-Port Klang). However, Amirudin had previously claimed that land clearing operations in the state's forest reserves had been carried out "without approval," noting that a police report had been filed against CCCC in December. Denis clarified that Amirudin was not referring to the lack of a permit to work on the project, but rather the lack of approval from the state Forestry Department to start clearing state land.
Amirudin and Hee were responding to a complaint made by the environmental watchdog Rimba Disclosure Project regarding the clearing of land. According to a CCCC spokesman, the organisation has all the necessary approvals and permits from the necessary authorities to move forward with the project. On December 21, Prime Minister Datuk Seri Anwar Ibrahim declared that the ECRL project would now cost RM74.96 billion to complete, down from the initial estimate of RM85.97 billion when the project was first announced in 2017.
He declared that the project to build the 665km-long rail system from Kota Baru in Kelantan to Port Klang in Selangor will move forward.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VPG3413
SELANGOR
BSF4817
JOHOR
JYA4522
PULAU PINANG
PRR4731
PERAK
ANW6390
PAHANG
CFC1267
KEDAH
KGA9280
NEGERI SEMBILAN
NEG2280
KOTA KINABALU
SJL2895
KUCHING
QAB5081L
Last updated 16 Jun, 2025
Fuel Price
Petrol
RON 95
RM 2.05
RON 97
RM 3.07
RON 100
RM 5.00
VPR
RM 6.23
Diesel
EURO 5 B10
RM 2.74
EURO 5 B7
RM 2.94
Last updated 12 Jun, 2025
Related News
ECRL Is More Than 60% Complete - Malaysia Rail
ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.
25-03-2024
ECRL Project Progress Surpasses 56% - Loke
ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.
11-12-2023
ECRL Kelantan Expected To Be Completed Six Months Earlier
The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.
26-06-2023
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke
The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.
12-04-2023
ECRL Project In Terengganu Reaches 55% Progress
The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.
05-04-2023
ECRL's Kuantan Tunnel Ready By April; Overall Project Progress at 40%
ECRL project's Kuantan Tunnel will be completed by the end of April.
08-03-2023
Kelantan And Terengganu ECRL Project Affected By Floods
The floods last week impacted around 70% of the construction work at sections 1 and 2 of the East Coast Rail Line (ECRL), which spans 82 kilometres from Tunjong here to Setiu in Terengganu.
28-12-2022
ECRL Will Continue - Loke Siew Fook
The federal government will continue the RM50 billion East Coast Rail Link (ECRL) project, according to Loke Siew Fook, the minister of transportation.
07-12-2022
Latest News
PLUS Opens Three New Lanes At Rawang Selatan Toll Plaza
PLUS has announced the addition of three new lanes at the Rawang Selatan toll plaza (Exit 115).
16-06-2025
RON95 Petrol Subsidy Rationalisation Will Proceed – PMX
The government will proceed with the RON95 fuel subsidy rationalisation, says Prime Minister Anwar Ibrahim.
16-06-2025
Car Wash Worker Severely Injured After Vehicle Plunges From 3rd Floor
A car wash worker driving a customer’s Toyota Camry crashed through the wall of a building in Old Klang Road on Sunday.
16-06-2025
Roslan Abdullah Joins GWM Malaysia As New COO
Former deputy CEO of Proton Roslan Abdullah appointed as new COO at GWM Malaysia.
16-06-2025
Mustang, BMW Owners Caught With Expired Road Tax, Citing Financial Issues
Financial issues cited by Mustang and BMW X5 owners caught with expired road tax during JPJ operation.
16-06-2025
Nanta: Damaged Road Surface Linked to Cyclist’s Death
Road damage blamed on heavy lorry traffic; urgent repairs ordered following fatal crash.
16-06-2025
Gerik Crash: No signs Of Brake, Steering Failure
Preliminary investigations into the fatal June 9 bus crash in Gerik, have not revealed any technical malfunctions.
15-06-2025
Gerik Crash: Motac Urges Return Of Authority Over Tourism Vehicles
In response to the fatal bus crash involving UPSI students, Motac aimed to regain control over tourism transport for safety reasons.
13-06-2025
Show More
trending_flat