ECRL Land-Clearing; Enforcement Due To SOP Breach - Selangor MB’s Aide

According to state government staffer Jay Jay Denis, a Chinese construction company responsible for clearing land in Selangor's forest reserves for the East Coast Rail Link (ECRL) project was subject to enforcement action last year for failing to follow standard operating procedures.
Despite having a permit to work on the ECRL, China Communications Construction Company (M) Sdn Bhd (CCCC) started construction on that part of the project in Selangor in December of last year before getting the go-ahead from the state Forestry Department.

"They (CCCC) believed they could start working right away because they had the permit, but they actually needed to apply to the department to let authorities know they would be beginning work.
When contacted, he explained, "This is so that the department can send personnel to the site to ensure that the proper parts of the forests are being carved out."

The stop-work order and fine that were imposed on the company in December have since been lifted, according to the special officer to Selangor Menteri Besar Datuk Seri Amirudin Shari. "The company was informed in December that they will need to follow the proper administrative procedures in order to start working in the future.
The problem back then was simply that they failed to give a notice (to the department), he said. "If (CCCC) had no permit to operate then, there would definitely have been further legal action," he said.
Denis' remarks follow yesterday's statement by state executive councillor Hee Loy Sian that a use permit had been issued by the department in July 2022 for the execution of the ECRL project in the permanent forest reserve area.
The head of the state's Environment, Green Technology, Tourism, and Orang Asli Affairs Committee also stated that on November 30, 2021, Malaysia Rail Link Sdn Bhd, the department of the Finance Ministry in charge of managing the ECRL project, received approval for the environmental impact assessment report for Section C2 (Gombak-Serendah-Port Klang). However, Amirudin had previously claimed that land clearing operations in the state's forest reserves had been carried out "without approval," noting that a police report had been filed against CCCC in December. Denis clarified that Amirudin was not referring to the lack of a permit to work on the project, but rather the lack of approval from the state Forestry Department to start clearing state land.
Amirudin and Hee were responding to a complaint made by the environmental watchdog Rimba Disclosure Project regarding the clearing of land. According to a CCCC spokesman, the organisation has all the necessary approvals and permits from the necessary authorities to move forward with the project. On December 21, Prime Minister Datuk Seri Anwar Ibrahim declared that the ECRL project would now cost RM74.96 billion to complete, down from the initial estimate of RM85.97 billion when the project was first announced in 2017.
He declared that the project to build the 665km-long rail system from Kota Baru in Kelantan to Port Klang in Selangor will move forward.
Written By
Anis
Previously in banking and e commerce before she realized nothing makes her happier than a revving engine and gleaming tyres........
JPJ Running Numbers
KUALA LUMPUR
VRF6242
SELANGOR
BSR5170
JOHOR
J9999J*
PULAU PINANG
PSD6921
PERAK
APJ7437
PAHANG
CFH1334
KEDAH
KGG9769
NEGERI SEMBILAN
NEK8753
KOTA KINABALU
SJT130
KUCHING
QAB1767P
Last updated 12 Jul, 2026
Fuel Price
Petrol
RON 95
RM 3.97
+1.38
RON 97
RM 4.90
+1.75
RON 100
RM 7.20
+2.20
VPR
RM 8.23
+2.00
Diesel
EURO 5 B10
RM 5.12
+2.08
EURO 5 B7
RM 5.32
+2.08
Last updated 30 Apr, 2026
Related News
ECRL Theft Case: 32nd Incident Recorded, RM3 Million in Cumulative Losses
The ECRL project has recorded its 32nd case of theft or vandalism along its alignment from Kota Bharu to Port Klang.
14-10-2025
ECRL Project Hits 87% Completion by August 2025 – MoT
The ECRL project has recorded 87% overall completion as of August 2025, said Transport Minister Anthony Loke.
23-09-2025
ECRL Could Extend to Sungai Golok After KTMB Revival – MRL CEO
MRL is not discontinuing the proposal to extend the ECRL line from its current final station in Kota Bharu to Sungai Golok.
24-06-2025
ECRL Is More Than 60% Complete - Malaysia Rail
ECRL has made 62.4% progress, says Chief Executive Officer of Malaysia Rail Link Sdn Bhd (MRL), Darwis Abdul Razak.
25-03-2024
ECRL Project Progress Surpasses 56% - Loke
ECRL project has surpassed 56% of its progress as of November, says Transport Minister Anthony Loke Siew Fook.
11-12-2023
ECRL Kelantan Expected To Be Completed Six Months Earlier
The ECRL in Kelantan is expected to be completed six months ahead of schedule in January 2027.
26-06-2023
"ECRL Construction 42% Complete, Developer Proceeds With Genting Tunnel" - Loke
The East Coast Rail Link (ECRL) is currently 42.06% complete, according to Transport Minister.
12-04-2023
ECRL Project In Terengganu Reaches 55% Progress
The construction progress of the ECRL project in Terengganu has reached 55.21%, while the overall ECRL project achieved 40.81 percent completion rate.
05-04-2023
Latest News
RXZ Tragedy At Jabor: A Fatal Wake-Up Call For Malaysia's Convoy Culture
The fatal RXZ convoy crash near Jabor has left many in shock. We look at the details behind the accident and the growing concerns over convoy road safety.
12-07-2026
No Helmet, No Exceptions: JPJ Confirms Summonses For Viral Campaign Convoy Riders
JPJ confirms summonses for helmetless riders in viral campaign convoys. Minister Anthony Loke emphasizes that safety laws apply to everyone, regardless
10-07-2026
No License, No Insurance, And Ketum: The Reality Behind JPJ’s Roadblock Crackdown
Over 91,000 vehicles inspected. More than 42,000 notices issued. These aren't just figures on a report, they represent a massive, ongoing shift in how authorities are policing our roads.
10-07-2026
Hybrid, Petrol, Or EV? Toyota’s Latest Sales Figures Prove Malaysians Love Having Options
UMW Toyota reports 36,200 units sold in 1H 2026. Discover how Toyota's "Multi-Pathway" strategy—from petrol and hybrids to EVs—is winning over Malaysian drivers.
10-07-2026
PSA: If You Don't Fix Your Chevy Airbag By 2026, Your Next Service Trip Is To Thailand
Your free window is closing. If you drive a used Chevrolet Cruze, Sonic, Trax, or Orlando in Malaysia, your factory airbag support expires in December 2026. Here is why you might have to drive to Thailand if you keep procrastinating.
08-07-2026
More Than A Service Centre? This New OMODA | JAECOO Outlet In Selayang Has A Coffee Lounge & Free Wi-Fi
Servicing your car shouldn't be a chore. Check out the new OMODA | JAECOO Selayang 3S centre, featuring a modern coffee lounge, free Wi-Fi, and top-tier service.
07-07-2026
This Lucky UiTM Student Is Driving Home A Brand New Perodua Myvi After Downloading P-Circle App
A 22-year-old UiTM student just scored a brand-new Perodua Myvi after downloading the P-Circle super app! Find out how she won the KLIMS 2026 grand prize.
07-07-2026
Netizens Are Calling PMX A Hypocrite For Riding A Bulletproof BMW 7 Series—But Here’s The Plot Twist
Netizens are calling PMX a hypocrite over a bulletproof BMW 7 Series. But here is the massive government plot twist behind the armored vault on wheels.
07-07-2026
Show More
trending_flat